Date Progress Photos
5-30

The foundation and the fireplace are begun.

Click Here to see the progress of the foundation and fireplace.
 
8-16

The framing begins.

Click Here to see the progress of the framing.
 
11-5

The electrical, plumbing and heating rough-ins are done and the insulation is in place.  The drywallers begin tomorrow.  In the meantime, the roof is almost finished and will be complete this week.

11-5_Insulation-w.jpg (26157 bytes) 11-5_Heating_Ductwork-w.jpg (20237 bytes)
 
11-18

The roof is finished in the nick of time.  (Yes, that is snow on the roof!) The rock wainscot is finished across the front and we are starting the cedar siding.  Meanwhile the drywall is in place and they are taping and texturing it.

11-18_cedar_siding-w.jpg (29024 bytes) 11-18_rock_wainscot-w.jpg (23139 bytes)
 
12-07

The drywall is taped and textured.  Today, the painters start priming and painting the interior.  The masterbath Jacuzzi is mounted and will be tiled as soon as the painters are done.  Meanwhile, the exterior siding is progressing.

12-07_living_room-w.jpg (15554 bytes) 12-07_master_bath-w.jpg (10360 bytes)
 
12-18

The painters are finishing the upstairs painting.  The garage is finished being painted and the garage doors are installed.  Meanwhile, the exterior siding is progressing.  Next week, the hickory floor in the living room starts going down.

12-18_front-w.jpg (23366 bytes) 12-18_garage_doors-w.jpg (18310 bytes)
 
1-2

The hickory floor is installed and will be sanded and finished next week.  It doesn't look like much in this photo, but look at the photo below to see how it comes out!  Meanwhile, the tilework is progressing, the interior is painted and the window - door trim installation is underway.  The kitchen cabinets will be installed next week.

1-2_hickory_floor-w.jpg (18193 bytes)
Living Room with log railing
1-2_masterbath_tile-w.jpg (18813 bytes)
Masterbath
 
1-10

Everything is coming together quickly.  The hickory floors came out great.  This week, we are finishing the window and door trim plus installing the interior doors.  The heating is done and the cabinets will be finished next week.  We are doing granite tile countertops.  The far right photo is of the burl on the front column in the living room.

1-10_hickory_floor2-w.jpg (18300 bytes)
Finished Hickory Floor
1-10_front_column-w.jpg (16445 bytes)
Burl on Front Column
 