| View Site Plan & Elevations | ||||||||
| Date | Progress | Photos (Click Photos to see enlargements) |
||||||
|
5-07 |
The preliminary excavation is done and the foundation footers and stem walls will be poured next week. We were delayed getting started by the heavy rains this spring. Completion should be in October, just in time for the Holidays. |
![]() The driveway to the build site. |
![]() The actual build site. |
|||||
|
5-10 |
The footers are poured. Next, the stem walls will be formed and poured. |
![]() The footers are poured. |
![]() The footers from another angle. |
|||||
|
5-20 |
The stemwalls are poured. Next, we will backfill inside the stemwalls, do the rough-in plumbing that goes under the slab, and then pour the slab. |
![]() The stemwalls are poured. |
![]() A close up of the stemwalls. |
|||||
|
6-10 |
The slab is poured and the basement framing has begun. Once the subfloor is framed, the excavator will back fill around the rear wall and grade the driveway. |
![]() Framing Begins. |
![]() View from the future deck. |
|||||
|
7-3 |
The walls are framed and sheeted. The roof trusses are being installed. Next week, the roof will be sheeted and the plumbers and electricians will start their rough-ins. |
![]() The roof trusses are placed. |
![]() Note the cathedral ceiling shape in the living room.. |
|||||
|
7-14 |
The interior framing is almost complete as is the roof sheeting. The plumbers and electricians start their rough-ins this week. |
![]() View from the master bedroom. |
![]() The interior framing is almost done. |
|||||
|
7-30 |
The plumbing and electrical rough-ins are done and inspected. The propane fireplace is installed and ready for the rock work. Tomorrow the insulation crew will begin. |
![]() Plumbing in utility room. |
![]() The covered deck is ready for the log railing. Note the Trex deck. |
|||||
|
7-30 |
The windows and cedar siding are being installed. Note the large windows in the living-dining room. The drywall crew starts next Monday. |
![]() The prow front. |
![]() The cedar siding is going on. |
|||||
|
8-6 |
The cedar siding is almost done and the roof metal will be finished this week. The insulation is installed and the drywall is well underway. It will be textured next week. |
![]() The cedar siding. |
![]() The insulation is done and the drywall is being installed. |
|||||
|
8-23 |
The drywall is finished and the primer is done. Next week the painter will finish the walls and the finish carpenter will start triming the windows and doors. Also, the rock mason will build the fireplace wall. Meanwhile, the final grading is being completed including the natural rock retaining wall. |
![]() The drywall and primer are done. |
![]() The natural rock retaining wall.. |
|||||