Payette River Sub. Home 
Lot 34
Current Building Progress


 

View Floorplan

View Home Features

View Site Plan & Elevations
 
Date   Progress Photos
(Click Photos to see enlargements)

5-02

 

The well is drilled and the permits have been submitted for approval.  Excavation work for the foundation is expected to begin in mid-May.


The creek beside the building site.

 

5-22

 

Excavation for the foundation began today.  Next week, the concrete crew starts pouring the footers and stemwalls.

5-21-02_excavation.jpg (33544 bytes)
Digging out for the craw space.
5-21-02_excavation2.jpg (33343 bytes)
The excavation will take about 2 days.
 

6-12

 

The foundation is done and the excavator is backfilling around it and doing the final grading.  The power is installed.  The blue styrofoam is insulation for in the crawlspace.  Framing starts today.


The foundation is backfilled.

The crawlspace insulation is installed..
 

6-21

 

The garage floor slab is poured and the sub floor is down. The walls are going up.  Next week the trusses will be craned into place.


The house overlooking the creek.

The walls are going up.
 

7-19

 

The roof is sheeted and dried in.  Today the electrical and plumbing rough-ins were completed.  Next week the insulation goes in and then the drywall.


The trusses going up.

The roof is sheeted and dryed in.
 

7-30

 

The roof metal is almost done.  The drywall is Next week the siding and rock wainscoting will begin.


The insulation is done
and the drywall is begun.

The roof metal is going on.
   
 

8-17

 

The siding is on and the rock work is progresssing well.  Meanwhile, the drywall is installed, textured and ready for paint.


The drywall is textured.

The siding is on and the rock wainscoting is going on.
 

9-07

 

The interior is painted and the wainscoting is complete.  The interior trim carpenter and the tile contractor start this week.


The rock wainsccting.

The covered front entryway.
 

9-20

 

The interior is tile and interior trim are progressing nicely.  The log railing is installed.  The tile shower and whirlpool enclosure will be done next week.


The entry tile is done.

The log railing & stairs.
 

9-25

 

The tile shower and whirlpool enclosure are nearly complete.  The cabinets will start being installed next week.


The exterior is complete

The master bath.
 

See Payette River Lot 34 Features

 

See Payette River Lot 62 Building Progress

 

See Payette River Lot 49 Building Progress

   

See Highlands Lot 18 - Schrimsher Home Finished Photos

 

See Highlands Lot 8 - Stine Home Finished Photos

 

Return to Schrimsher Construction

 

Return to Engen Realty