April 15

 

Construction has begun!  The excavation will be finished this week and the footers will be poured for the foundation.

4-15_foundation.jpg (21452 bytes)
View of Meadows Valley 
4-15_foundation2.jpg (30331 bytes)
The daylight basement is excavated.
 

April 25

 

The footers are poured and the daylight basement concrete walls are being formed.  They will be poured next week.  Then the basement plumbing will be installed and the slab will be poured.
     The well is drilled with great results:
225' deep and 35 GPM.  

4-25-02_concrete_walls.jpg (28719 bytes)
Forms for basement walls.
4-25-02_well_driller.jpg (21691 bytes)
 

May 15

 

The basement slab is poured and the basement framing has begun.  This week the house will really start taking shape as the sub floor and the walls for the main floor will start to go up. 

5-17_framing.jpg (23855 bytes)
Framing for the basement walls.

View out the living room window.
 

May 30

 

The framing is well underway with about half of the trusses in place.  The roof sheeting will go on next week and then the plumbers will start their rough in.


The roof trusses are going up.

Overview of the site showing the views and the rear of the house.
 
June 12  

The roof and trim are going on.  Meanwhile the plumbing, heating and electrical rough-ins are being installed.  The exterior should be complete by the end of next week.


The roof shingles are going on.

The cedar trim is being installed.
 
June 21  

The exterior is complete with roof and siding.  The electrical, plumbing and heating rough-ins will be finished today.  Monday, the insulation begins and the drywall on Wednesday.


The
view from the front deck.  Note the log railing and Trex decking.

The fireplace / entertainment center is framed and ready for the cultured rock.
 
July 16  

The drywall has been hung and is being textured.  Meanwhile, the cultured rock fireplaces and wainscotting are almost finished.  Interior painting starts next week.


The downstairs gas fireplace.

The cultured rock wainscoting.
 
Sept. 9  

The house is nearing completion.  The cabinets will be installed next week as well as the carpet.  The interior trim is almost finished.   Everything should be complete by October 1.

 
 