|
||||||||
|
|
||||||||
| Date 2002 |
Progress | Photos (Click Photos to see enlargements) |
||||||
|
April 15 |
Construction has begun! The excavation will be finished this week and the footers will be poured for the foundation. |
![]() View of Meadows Valley |
![]() The daylight basement is excavated. |
|||||
|
April 25 |
The footers are poured and the
daylight basement concrete walls are being formed. They will be
poured next week. Then the basement plumbing will be installed and
the slab will be poured. |
![]() Forms for basement walls. |
![]() |
|||||
|
May 15 |
The basement slab is poured and the basement framing has begun. This week the house will really start taking shape as the sub floor and the walls for the main floor will start to go up. |
![]() Framing for the basement walls. |
![]() View out the living room window. |
|||||
|
May 30 |
The framing is well underway with about half of the trusses in place. The roof sheeting will go on next week and then the plumbers will start their rough in. |
![]() The roof trusses are going up. |
![]() Overview of the site showing the views and the rear of the house. |
|||||
| June 12 |
The roof and trim are going on. Meanwhile the plumbing, heating and electrical rough-ins are being installed. The exterior should be complete by the end of next week. |
![]() The roof shingles are going on. |
![]() The cedar trim is being installed. |
|||||
| June 21 |
The exterior is complete with roof and siding. The electrical, plumbing and heating rough-ins will be finished today. Monday, the insulation begins and the drywall on Wednesday. |
![]() The view from the front deck. Note the log railing and Trex decking. |
![]() The fireplace / entertainment center is framed and ready for the cultured rock. |
|||||
| July 16 |
The drywall has been hung and is being textured. Meanwhile, the cultured rock fireplaces and wainscotting are almost finished. Interior painting starts next week. |
![]() The downstairs gas fireplace. |
![]() The cultured rock wainscoting. |
|||||
| Sept. 9 |
The house is nearing completion. The cabinets will be installed next week as well as the carpet. The interior trim is almost finished. Everything should be complete by October 1. |
![]() |
||||||