| View Front Elevation | ||||||||
| Date | Progress | Photos (Click Photos to see enlargements) |
||||||
|
3-14 |
The floor joists and subfloor are installed. The walls will start going up next week. Also, the power and water line will be run. |
![]() The floor joists are going down. |
![]() The subfloor is glued and nailed down. |
|||||
|
3-27 |
The subfloor is done and the walls are going up. The water and sewer lines are installed. Next week, the trusses will go on and then the roof. |
![]() The garage and walls are framed |
![]() The shear walls are going up. |
|||||
|
4-15 |
The trusses are in place and the cathedral roof rafters over the living room will be placed next. |
![]() The trusses are in place. |
![]() The roof is sheeted. |
|||||
|
4-30 |
The rafters are done and the entire roof is papered and ready for the roofing metal. Meanwhile the plumbers are almost finished with their rough-in. Next, the electrician does his rough-in. |
![]() The living room joists are placed and the roof is completely sheeted. |
![]() The 2nd bathroom's bathtub. |
|||||
|
5-12 |
The log siding is progressing. The plumbers and electrician are done with their rough-ins. The insulator and drywallers start this week. |
![]() The log siding is nearing completion. |
![]() The owner has elected to install a rock wainscoting beneath the log siding. |
|||||
|
5-22 |
The insulation is done and the drywallers are well underway. They should finish next week and the painters will start. |
![]() The drywall is going up. |
![]() The insulation go in before the drywall. |
|||||