| View Site Plan & Elevations | ||||||||
| Date | Progress | Photos (Click Photos to see enlargements) |
||||||
| Oct. 12 |
The drywall is finished and the painters are painting the interior. Meanwhile, the cedar siding and roof are going on. |
. |
![]() |
|||||
| Oct. 25 |
The garage door is hung and the entry way tile is installed. |
. |
![]() |
|||||
| Oct. 30 |
The hickory floors are installed and have the first coat of finish. The fireplace is framed and the insert is installed. |
![]() |
![]() |
|||||
| Nov. 18 |
The fireplace is finished and the interior is almost finished. The carpet will soon be installed in the bedrooms. The cabinets arrive this week. |
. |
![]() |
|||||